The U.S. Department of Energy has directed a west Michigan coal plant to remain available through Feb. 12, 2027, giving the regional grid operator another winter with a power station that was due to retire in May 2025. The seventh emergency order for the J.H. Campbell plant in West Olive took effect Sunday, Nov. 15.

Energy Secretary Chris Wright signed the order Nov. 13. It requires Consumers Energy and the Midcontinent Independent System Operator, or MISO, to keep the 1,420-megawatt plant ready to run. It directs MISO to dispatch the plant only during the hours needed to meet the emergency and to minimize costs. The order also requires daily reports to the department on whether the plant ran and calls for a report by Nov. 28 on how the operator is keeping it available.

Why the department says the grid needs Campbell

The department cited the risk of high winter electricity demand and a shortage of power plants that can generate on demand. In the order, it pointed to emergency steps MISO took during January’s Winter Storm Fern and to longer-term projections about demand growth and power plant retirements. Michigan had already planned for Campbell’s retirement, and Consumers Energy acquired a 1,200-megawatt gas plant in Covert. The department argues that winter conditions can still leave the region with too little power at peak times.

A federal appeals court in September set aside the department’s original May 2025 order. The three-judge panel found that the circumstances the department cited for that order did not establish an emergency under the Federal Power Act and that the department had exceeded its authority. The ruling addressed that expired order. The latest directive is a separate order, and the department’s request for the full court to reconsider the September ruling was still pending Monday.

Who could pay to keep the plant available

A steel power transmission tower in Ypsilanti Township, Michigan.
A transmission tower in Ypsilanti Township, Michigan, photographed in August 2013.Dwight Burdette / Wikimedia Commons · CC BY 3.0

Consumers Energy said in its quarterly filing that it expected to seek recovery for $303 million in net costs through Sept. 30, including amounts it had already requested. That figure accounts for $344 million in revenue from the regional electricity market. It covers earlier orders and excludes costs under the latest extension, which began in November.

The utility has sought to spread the costs across MISO’s North and Central regions. That would put part of the cost outside Michigan if federal regulators approve the proposed allocation. According to the same filing, the Federal Energy Regulatory Commission directed MISO to revise the tariff that governs how it allocates costs, but rejected MISO’s initial filing. A revised filing submitted in April was still pending at the time of the utility’s report. The $303 million figure does not establish a charge for any particular household.

The Environmental Defense Fund opposed the extension on Monday, arguing that customers in the region would bear the expense of keeping an uneconomic plant available. The next regulatory decisions will determine how much of the earlier costs the utility can recover and where those costs would fall.