The Energy Department has offered up to $2.8 billion in conditional financing for Wyoming Intertie, a proposed power connection between the eastern and western U.S. grids. Announced November 17, the commitment could help pay for infrastructure that moves electricity to where it is needed, with potential benefits for customers far beyond Wyoming.

The project still needs permits, land rights and commercial contracts. Its developer's schedule places possible operation in 2032 or 2033. The department's projected $39 billion in electricity savings is a regional forecast, with no promised reduction on an individual customer's next bill.

What the federal commitment covers

The Energy Department's announcement describes a conditional commitment from its Office of Energy Dominance Financing. Technical, legal, environmental and financial conditions must be satisfied before the department signs definitive financing documents and funds the loan.

Grid United, the developer, says the proposed 30-year loan would cover 80% of construction costs. The $2.8 billion amount excludes interest during construction. Its financing fact sheet lists full rights-of-way, capacity contracts, permits and compliance with federal program requirements among the closing conditions. Loan advances would begin after the project receives notice to proceed and enters construction.

Capacity contracts are agreements with customers for space on the transmission line. Securing those customers is part of the financing process; the federal announcement does not establish that the line's entire capacity has been sold.

How a Wyoming line can help other states

Equipment and a worker inside the Celilo converter station in Oregon
An archival Energy Department photograph of the Celilo converter station in Oregon, part of the separate Pacific Intertie. Converters let power pass between systems that operate independently.Photo: U.S. Department of Energy / Wikimedia Commons, public domain.

The proposed route runs roughly 106 miles through Carbon, Albany and Platte counties, connecting substations near Medicine Bow and Wheatland. It would add up to 1,800 megawatts, or 1.8 gigawatts, of transfer capacity.

That figure measures how much power the connection could move. Wyoming Intertie would carry electricity generated elsewhere, with flows in either direction according to demand. Grid United's project description says it would carry all sources of generation.

The eastern and western grids operate largely independently. In its 2021 explanation of the Interconnections Seam Study, DOE described the small amount of electricity that could pass between those enormous networks through existing converter stations.

Converters change alternating current to direct current and back again, allowing grids that are not synchronized to exchange power. Wyoming Intertie plans a back-to-back converter station for that purpose. A larger connection can give operators access to generation on the other side when local demand surges or weather limits supply.

DOE's earlier study illustrated the opportunity: southwestern solar power could help meet eastern demand, while midwestern wind could flow west as the sun sets. Those were modeled regional examples, not a dispatch schedule for this proposed line.

What the savings estimate means for bills

DOE estimates up to $39 billion in electricity cost savings across 17 states in the Western Electricity Coordinating Council and Southwest Power Pool regions. That total describes potential system benefits. The announcement provides no household allocation or guaranteed monthly discount.

The economic case depends partly on being able to buy or move cheaper power between regions. In an August announcement of its separate connection study, SPP cited average price differences of $18 to $33 per megawatt-hour along the seam between its eastern footprint and the western grid, based on DOE's draft transmission-needs study.

Those wholesale price differences help explain the interest in more connections. They are not a quoted residential electricity rate, and they cannot be multiplied by a household's usage to calculate a promised saving.

When construction could begin

Wind turbines and power lines near Medicine Bow, Wyoming
Wind turbines near Medicine Bow, Wyoming, in May 2012. Wyoming Intertie would carry electricity from all generation sources.Photo: Tony Webster / Wikimedia Commons, CC BY 2.0.

Grid United's schedule puts permitting completion in 2029 and the earliest start of transmission-line and converter construction in 2030. Commercial operation is projected for 2032 or 2033, depending on procurement of the converter equipment.

The route remains proposed. The developer's permitting explanation lists a Wyoming Industrial Siting permit, county conditional-use permits and a federal environmental review under the National Environmental Policy Act. Construction depends on securing the land rights and regulatory approvals.